IST (Integrated System Testing) tests of the Hercules D / M 600P unit with the MTU Mercedes engine

Over the weekend, for one of our clients, we carried out the Integrated System Testing (IST) tests of the Hercules D / M 600P unit supplied by us with the MTU Mercedes engine. All tests lasted about 30 hours using a resistive load with a reactance module during which the aggregate worked in the 30-110% load range.
A step load test of the unit with 70% of PRP power was performed according to the standard.
During tests, our engineers monitored the parameters of the network analyzer and the electrical connections with the thermal imaging camera.
The last phase concerned work under the current building load along with the verification of power failure variants on the building.1 MTU